1717 Bissonnet

Platting, Permits & Construction Start Date

The property has been platted as an unrestricted reserve, having been recorded in mid-July 2007. The plat was without variance and did not require a hearing.

Utility capacity reservations were issued by the City of Houston in June and December of 2006.  Construction of a new public sanitary sewer (required as a condition of the capacity reservation) was completed and all utility impact fees were paid to the City of Houston as required in June 2007.

Water and sewer connections have been approved by the City of Houston.

A complete application for a foundation permit was filed with the City of Houston on July 30, 2007.  To date, the development site plan approval and a number of departmental approvals have been granted by the City of Houston.  A foundation permit has not yet been issued.

A voluntary Traffic Impact Analysis was submitted to the City of Houston in August 2007 and approved on September 4, 2007.  The approval was subsequently rescinded on September 28, 2007.

Construction is anticipated in spring/summer of 2008.